3.2 Substation Location 8 & 9

Table 4 - Substation Location 8 & 9 Delivery Route Summary

Ref

Drawing

Chainage

Description

Photo (Appendix 3)

3.2.1

62501721-DRG-102

100

Right Turn of A1. Fenceline to be removed.

1

3.2.2

62501721-DRG-102

100

Right turn off A1, temporary overrun area
required over central reservation

2

3.2.3

62501721-DRG-102

100

Right Turn off A1, Road sign/Island to be removed

3

3.2.4

62501721-DRG-102

200

Left Turn to main access route, large overrun area to be built up.

4/5

3.2.5

62501721-DRG-102

200

Left turn to main access route, Manhole load capacity to be check

6

3.2.6

62501721-DRG-102

450

Existing fenceline to be removed

9

3.2.7

62501721-DRG-102

450

Overrun area to be granular surfaced

/

3.2.8

62501721-DRG-102

700

Overhead lines  ok

10

3.2.9

62501721-DRG-103

760

Manhole load capacity to be checked

/

3.2.11

62501721-DRG-103

770

Fenceline to be removed to accommodate
overhang

11

3.2.12

62501721-DRG-103

880

Overrun area to be granular surfaced

12

3.2.13

62501721-DRG-103

1040

Culvert to be structurally assessed. No information was determined on the details of the culvert due to limited access.

13

3.2.14

62501721-DRG-103

1070

Overrun area to be granular surfaced

/

3.2.15

62501721-DRG-103

1180

Overrun area to be granular surfaced

/

3.2.16

62501721-DRG-103

1200

Manhole load capacity to be checked

14

3.2.17

62501721-DRG-103

1230

Fenceline to be removed to accommodate
overswhang

15

3.2.18

62501721-DRG-104

1650

overhead lines avoided

16


3.3 HGV – Cable Road Crossing 1

Table 5 - HGV - Cable Road Crossing 1

Ref

Drawing

Chainage

Description

Photo (Appendix 3)

3.3.1

62501721-DRG-112

490

Road over railway bridge to be structurally assessed for HGV

1/2

 

3.4 HGV – Cable Road Crossing 2

Table 6 - HGV - Cable Road Crossing 2

Ref

Drawing

Chainage

Description

Photo (Appendix 3)

3.4.1

62501721-DRG-112

175

Road over water crossing to be structurally assessed for HGV. Limited details and  dimensions of the bridge due to restricted access.

1

3.4.2

62501721-DRG-112

200

Stone wall to be removed and earthworks required for vehicle over run

2

3.4.3

62501721-DRG-112

225

Road below railway bridge suitable for HGV

3/4


4 Structural Constraints

 

For each proposed delivery route, a structural assessment is required to ascertain the suitability of the structures along the route prior to delivery. The structures include bridges, culverts and watercourse crossings. Capacity of manholes highlighted in Section 3 along each route should also be confirmed. Note Sweco have been advised not to consult with local roads authority, network rail etc. at this stage.

 

The following sections highlight each structure that requires an assessment for the given route. 

 

4.1 Substation Location 3

 

The delivery route to the proposed substation location 3 will require the delivery vehicle to traverse a stone railway bridge. The location of the railway bridge is shown in Figure 41.

 

Railway bridge west parapet to be dismantled prior to delivery in addition to assessment of the bridge for the abnormal loads. Initial approvals from Network Rail and Transport Scotland will be required.

Figure 41 Railway bridge Crossing for Delivery to Substation Location 3

4.2 Substation Location 8 & 9

 

The delivery route to the proposed substation location 8 and 9 will require the delivery vehicle to traverse a culvert. The location of the culvert is shown in Figure 42. The make-up of the culvert could not be confirmed due to dense and overgrown vegetation.

 

An assessment of the culvert for the abnormal load is required. Note that no information was determined on the details of the culvert due to overgrown bushes and limited access.

Figure 42 Culvert Road Crossing for Deliver to Substation 8 & 9

4.3 HGV - Cable Road Crossing 1

 

The delivery route to the trenched cable road crossing 1 will required the HGV to cross a railway bridge. The location of the bridge is shown in Figure 43.

 

An assessment of the railway bridge crossing for the HGV is required.

Figure 43 Railway Bridge Crossing for Cable Road Crossing 1

4.4 HGV - Cable Road Crossing 2

 

The delivery route to the trenched cable road crossing 2 will require the HGV to cross a watercourse crossing. The location of the crossing is shown in Figure 44.

 

An assessment of the watercourse crossing for the HGV is required. Note that limited details and dimensions of the bridge were obtained due to restricted access.

Figure 44 Watercourse Crossing for Cable Road Crossing 2


5 Permanent Access Road Proposal

No ground investigation reports have been provided at this stage with respect to design of the permanent access roads. Therefore, proposals for the following road make-up have been provided in appendix D:

  • Floating access track (level or gently sloping topography);
  • Founded access track (level or gently sloping topography);
  • Founded access track – Track Construction Benched (on sloping topography).

6 Construction Cost Estimate

 

A cost estimate (+25%/-15%) for the new access road construction and improvements to current infrastructure has been assessed using values calculated from Spon’s Civil Engineering and Highways Work Price Book, the Estimator’s Pocket Book and information provided by contractors.

 

A preliminary assessment of the permanent access road was undertaken in lieu of ground investigation information. This assessment considered data from British Geological Survey maps. Given the road construction cost is sensitive to change and accounts for most of the overall cost, a lower and upper bound cost was used in the estimations.

 

Areas of temporary granular fill are based on vehicle overrun only. Earthwork requirements are subject to more detailed review as part of route temporary works design.

 

An estimate of the costs for each substation route is presented in Table 7 with the detailed estimate presented in Appendix E.

 

Table 7 - Substation Access Road Construction Cost Estimate

Substation

Estimated Construction Cost Range

Substation Location 3

£506,243

£862,806

Substation Location 8

£187,111

£278,978

Substation Location 9

£225,646

£348,842

 

It is advised to obtain a more detailed cost estimate from several contractors once topographical data and ground investigation information are made available. Note prices will vary between contractors and are subject to market conditions.