16.4. Tertiary Mitigation
A perimeter fence will be erected around the substation which will offer screening to EMFs generated by the equipment within the substation.
EMFs from the cables will be screened by the way the cables are manufactured, being insulated and installed within sheaths, and being primarily buried underground.
Where sections of cables may be required to be OHL these will similarly be screened by the way they are manufactured, with OHL’s designed in compliance with ICNIRP 1998 exposure limits. Construction and operation of the Proposed Development would be in compliance with The Control of Electronic Fields at Work Regulations (2016) which ensures that levels of EMF are within safe limits.
16.5. Potential Proposed Development Impacts
The Proposed Development will generate EMFs from both onshore cable circuits and from the equipment housed within the substation.
Due to the likely distance from the substation components to the closest publicly accessible point (outwith the perimeter fence), the greatest exposure to EMFs is likely to be from the onshore cables, however due to the manufacturing design of either underground or OHL cables, limited EMFs, if any, will be experienced. The maximum EMF level that the public will be exposed to will be significantly below the guideline for public exposure limits which are set to protect health (ICNIRP, 1998).
The Proposed Development will be designed and operated in accordance with all relevant health and safety legislation and the occupational exposure guidelines for EMF.
16.6. Receptors and Impacts Scoped In and Out of Assessment
Table 16.1 below summarises the potential impacts proposed to be scoped in and out of the EIAR.
It is considered that EMFs from the Proposed Development will not be significant to cause any public health risk and as such potential effects from EMFs are scoped out and further assessment of EMF is not required within the EIAR. It is also proposed that a standalone section addressing ‘Population and Human Health’ will not be required within the EIAR, with any potential human health effects being assessed within the other environmental topic sections where relevant e.g. noise or traffic and transport.
16.7. Scoping Questions to Consultees
- Do consultees agree with the proposed approach to scope out further assessment of EMFs?
- References
References
- Department of Energy & Climate Change (2012). Power Lines: Demonstrating compliance with EMF public exposure guidelines – a voluntary code of practice. Accessed at: https://www.gov.uk/government/publications/demonstrating-compliance-with-emf-public-exposure-guidelines-voluntary-code-of-practice
- ICNIRP (1998). ICNIRP Guidelines for limiting exposure to time-varying electric, magnetic and electromagnetic fields. Available at: http://www.icnirp.org/cms/upload/publications/ICNIRPemfgdl.pdf
- UK Government (2016). The Control of Electromagnetic Fields at Work Regulations. Accessed at: http://www.legislation.gov.uk/uksi/2016/588/contents/made
- SUMMARY OF SCOPING REPORT
SUMMARY OF SCOPING REPORT
Table 17.1 below summarises the impacts and receptors which the Applicant proposes to scope in and out of the EIAR for the Proposed Development. We would be grateful if consultees could review and confirm agreement, or otherwise, with the scope outlined in Table 17.1.
Annex A – Outline Schedule of Environmental Commitments (Tertiary Mitigation)
Technical Discipline | Environmental Commitment | Implementation Phase | |
---|---|---|---|
General | The Applicant will produce a draft CEMP, to include the following:
| Construction | |
General | A Proposed Development Communication Plan will:
. | Pre-construction and Construction | |
Landscape and Visual | The siting of the substation, landfall(s), access tracks and cable route will be selected with the sensitivity of landscape and visual resources in mind to help avoid or reduce the potential impacts . | Design | |
Ecology and Ornithology | Opportunities for biodiversity enhancements, such as planning species-rich hedgerows and establish and manage species-rich grasslands, within the site will be identified | Design | |
Ecology and Ornithology | Watercourse crossings will be designed to enable passage by mammals where reasonably practicable. | Design and Construction | |
Ecology and Ornithology | A suitably qualified Ecological Clerk of Works (ECoW) will be appointed. The ECoW will be present and oversee all construction activities as well providing toolbox talks to all site personnel with regards to priority species and habitats, as well as undertaking monitoring works and briefings to relevant staff and contractors as appropriate. | Pre-construction and Construction | |
Ecology and Ornithology | A Species Protect Plan (SPP) will be produced as part of the CEMP. The SPP will detail measures to safeguard protected species known to be in the area and will include for pre-construction surveys for protected species as well as ensuring the use of best practice measures during all construction activities. The SPP will describe the process to be followed in the case that new protected species are recorded on site that will therefore also need to be protected during construction works, as well ensuring the implementation of effective toolbox talks to raise awareness of site personnel to sensitive ecological receptors on site. | Pre-construction and Construction | |
Ecology and Ornithology | Best practice techniques to prevent pollution of watercourses within the site will be employed. These may include use of buffer strips, infiltration trenches, settlement swales or lagoons. | Pre-construction and Construction | |
Noise | Normal construction hours will be Monday to Sunday 07.00-19.00; any exceptions to this will be agreed in advance with ELC. | Construction and Decommissioning | |
Noise | Based on noise modelling results, where noise has the potential to cause disturbance the use of mufflers, acoustic barriers and screening will be considered | Construction and Decommissioning | |
Noise | The construction and decommissioning works would use Best Practicable Means (BPM) to limit the impacts of noise at sensitive receptors. | Construction and Decommissioning | |
Noise | Quieter equipment will be selected where reasonably practicable | Design | |
Noise | Acoustic enclosures and barriers will be installed | Construction | |
Noise | Where necessary, the substation will be screened further by the construction of a landform/embankment | Operation | |
Noise | Exhausts/outlets for air handling/cooling units will be silenced | Design | |
Noise | Equipment will be located to take advantage of screening inherent in the design, i.e. from the substation hall(s) or control room buildings where reasonably practicable | Design | |
Noise | Noise related complaints will be monitored | Construction and Operation | |
Air Quality | A Dust and Air Quality Management Plan will be authored and will include best practice measures in accordance with the Institute of Air Quality Management IAQM recommended guidance | Pre-construction and Construction | |
Air Quality | The Contractor will, in line with the Proposed Development Communication Plan:
| Construction | |
Air Quality | The Contractor will undertake air quality monitoring by:
| Construction | |
Air Quality | Measures to prepare and maintain the site will include:
| Pre-construction and Construction | |
Air Quality | Site operations will:
| Construction | |
Air Quality | The Contractor will:
| Construction | |
Cultural Heritage | Avoidance (within design limits ) of identified areas of archaeological constraint during the design of the Proposed Development | Design | |
Cultural Heritage | Minimisation of visual impacts on designated heritage assets (Scheduled Monuments, Listed Buildings, Conservation Areas, Gardens and Designed Landscapes, Historic Battlefields) will be minimised | Design | |
Cultural Heritage | Trial trench evaluation at areas of archaeological sensitivity, as identified through the results of geophysical surveys, will be undertaken | Pre-construction | |
Cultural Heritage | A further programme of construction phase archaeological mitigation will be agreed | Pre-construction | |
Cultural Heritage | A professionally qualified archaeological contractor would be appointed to act as an Archaeological Clerk of Works (ACoW) | Pre-Construction | |
Cultural Heritage | Construction phase archaeological guidelines would be provided to the Contractor for dissemination to all construction contractors, advising on the need to avoid adverse effects on buried archaeological remains | Construction | |
Cultural Heritage | Fencing off/marking out areas of constraint for avoidance during the construction phase would be carried out, where there are upstanding earthwork remains that require preservation | Construction | |
Cultural Heritage | Set piece excavations may be required where heritage assets (including buried archaeological remains) cannot be avoided | Construction | |
Cultural Heritage | Watching briefs/archaeological monitoring may be required in archaeologically sensitive areas during topsoil stripping and construction works as required under planning conditions | Construction | |
Cultural Heritage | Post-excavation analysis and reporting of any new discoveries made during set piece excavations or archaeological monitoring would be carried out to the satisfaction of ELCAS and in compliance with any planning conditions | Construction | |
Cultural Heritage | Landscaping mitigation will take account of the settings of designated heritage assets | Design | |
Geology, Hydrology, Soils & Flood Risk | Where practicable a 50m buffer will be implemented around all watercourses considered to have continuous flow throughout the year. Where it is not possible to maintain a 50m buffer i.e. where a watercourse will require to be crossed, these works will be regulated under the Controlled Activities Regulations (CAR) licensing regime and necessary licences will be sought from SEPA prior to construction works. | Design | |
Geology, Hydrology, Soils & Flood Risk | The draft CEMP will include a detailed drainage strategy and pollution mitigation measures which will be implemented in accordance with the SEPA’s guidance. This will include, but is not limited to:
| Pre-construction and Construction | |
Geology, Hydrology, Soils & Flood Risk | A Water Quality Monitoring Programme will be implemented before and during construction to record the pre-existing water conditions and ensure that no deterioration occurs during construction. | Pre-construction and construction | |
Geology, Hydrology, Soils & Flood Risk | The CEMP will contain a Soils Management Plan which will included, but not limited to, the following measures:
| Pre-construction and construction | |
Geology, Hydrology, Soils & Flood Risk | A Sustainable Urban Drainage System (SUDS) around the permanent infrastructure will be maintained and managed on a regular basis | Operation | |
Traffic and Transport | A Construction Traffic Management Plan will be developed and implemented. The hours of operation will be managed to mitigate the impact on sensitive receptors, with the construction access route chosen to minimise the impact on residential properties adjacent to the route, as far as possible | Construction | |
Socio-economics | No mitigation required. |
| |
Land Use, Tourism and Recreation | An Access Management Plan will be developed in consultation with ELC and be included within the CEMP. It will include measures to minimise temporary disruption to pedestrian access and include requirements for signage | Pre-construction and Construction | |
Land Use, Tourism and Recreation | Agricultural land not required through the operational phase will be reinstated to ensure it can return to agricultural use | Operation | |
EMF | A perimeter fence will be erected around the substation which will offer screening to EMFs generated by the equipment within the substation. | Design | |
EMF | The cables will be insulated, installed within sheaths, and primarily buried underground. | Design | |
EMF | Construction and operation of the Proposed Development would be in compliance with The Control of Electronic Fields at Work Regulations (2016). | Construction and operation | |